Marine Warranty Surveyor for MHI Vestas – 2018

Acted as marine warranty surveyor for several repair and maintenance projects in the UK.

Customer: MHI Vestas

 


Galloper Offshore Wind Farm – 56 Siemens Gamesa 6 MW – 2017

Client representative on crane vessel during turbine erection.

Customer: Siemens Gamesa


Veja Mate – 67 Siemens 6 MW – 2017

Client representative during turbine erection.

Customer: Siemens Gamesa


Block Island Offshore Wind Farm – 5 GE Energy Haliade 150 6 MW – 2016

Offshore Support to installation team.

Customer: GE Wind, France


Sand Bank Offshore Wind Farm – 72 Siemens 4.0 MW – 2015-2016

Approval of method statements and riskassesments for pile installation and turbine erection. Client representative on crane vessels during pile installation and turbine erection.

Customer: Vattenfall GmbH Germany

SF5 - May 5th 2013 - s002
DanTysk Offshore Wind – 80 Siemens 3.6 MW – 2013 -2014

Inspection of new build crane vessels. Approval of method statements and risk assessments for pile installation and turbine erection. Client representative on crane vessels during pile installation and turbine erection.

Customer: Vattenfall GmbH Germany

 

OLYMPUS DIGITAL CAMERA
Northwind – 72 Vestas 3 MW – 2013-2014

Inspection of crane vessel during construction.
Participated in several planning meetings.
Client representation on crane vessel during turbine erection.

Customer: Northwind – InControl S.A. Luxembourg        

 

aerial photoLondon Array Wind Farm – 175 Siemens 3.6 MW – 2011 -2012

Inspection and trial trips with new build crane vessels.
Approval of method statements and risk assessments for pile installation and turbine erection.
Client representative on crane vessels during pile installation and turbine erection.

Customer: London Array Ltd. UK (DONG, EON and Masdar)

OLYMPUS DIGITAL CAMERA
Walney II – 51 Siemens 3.6 MW – 2011

Supervision during installation of mono piles using a floating crane barge.

Customer: DONG Energy UK

Screen Shot 2014-05-28 at 14.34.47
Marine Warranty Surveyor for Siemens – 2011

Acted as marine warranty surveyors for Siemens for a repair project for 4 UK wind farms (Linn Inner Drowsing, Gunfleet Sands, Burbo Bank and Ryhl Flats) using MPI Resolution.
Approved all necessary material to do the operation and issued COAs. Followed repair jobs partly.

Customer: Siemens UK

Ormonde 004
Ormonde – 30 Repower 6 MW – 2011

Called in to improve installation speed of turbine erection.
Partly supervision of turbine erection.

Customer: Ormonde Offshore Wind Ltd. – Vattenfall Europe

 

004H!
Thanet Offshore Wind – 100 Vestas 3 MW – 2010

Inspection and preparation of installation vessel.
Supervision of windmill erection.

Customer: Thanet Offshore Wind Ltd. – Vattenfall Europe

 

Sprogø 2009 015
Sprogoe Offshore Wind Farm – 7 Vestas 3 MW – 2009

Inspection and preparation of installation vessel.
Supervision of windmill erection.

Customer: Vestas Offshore A/S

 

OLYMPUS DIGITAL CAMERA
Belwind 1 – 55 Vestas 3 MW – 2009

Different consultancy work.
Called in as independent surveyor during pile installation after 2 piles during tow out had sunk. Negotiations with Belgian authorities concerning tow out of piles.

Customer: Belwind B.V.

Robin RIgg
Robin Rigg Offshore Wind Farm – 60 Vestas 3 MW – 2008 -2009

Participated in production of method statements and risk assessments.
Inspection and preparation of installation vessels.
Supervision of windmill erection.

Customer: Vestas Offshore UK

Fahrt mit der Windforce1 von Ndd.Mole - alpha ventus
Alpha Ventus – 6 Repower 5MW – 2008

Followed building of installation vessel.
Supervision of turbine erection.

Customer: Vattenfall Germany

 

Prinses Amalia Windpark (Q7)Prinses Amalia Windpark (Q7) – 60 windmills each 2 MW – 2007-2008

Participated in production of method statements and risk assessments.
Inspection of Installation vessels.
Supervision of windmill erection.

Customer: Vestas Offshore NL

SVANEN
Egmond an Zee – 36 Vestas 3MW – 2007

Made all risk assessments for pile installation.
Approved method statements for pile installation and for turbine erection.
Safety officer on crane vessel during pile installation.

Customer: Ballast Nedam and Vestas NL

BOW - Pile 08 Drilling 016
Barrow – 30 Vestas 3 MW – 2005 -2006

Approved method statements and risk assessments for pile installation and turbine erection.
Client representative on crane vessel during installation on piles, laying interfiled cables and during turbine erection.

Customer: KBR and Vestas UK

KF Instalation pictures 019
Kentish Flats – 30 Vestas 3MW – 2004 -2005

Approved method statements and risk assessments for pile installation.
Followed UXO survey on survey vessel.
Client representative on vessels during pile installation and turbine erection.

Customer: Vestas UK

Horns Reef 1 2004
Horns Rev I (Refurbishment) 2004

80 Vestas 2MW
Involved in planning of refurbishment of all nacelles.
Client representative on crane vessels during project.

Customer: Vestas DK

DSCN0410
Scroby Sands – 30 Vestas 2MW – 2003 -2004

Approved method statements and risk assessments for pile installation and turbine installation.
Trouble shooting on cable laying.
Client representative on crane barge and vessel during installation of piles and turbine erection.
Client representative on vessel during stone dumping for scour protection.

Customer: Vestas UK

Northoyle
North Hoyle – 30 Vestas 2MW – 2003

Following conversion of jack up barge.
Helped to develop method statements and risk assessments for pile installation and turbine erection.
Client representative on crane barges during installation.

Customer: Vestas UK


Horns Rev 1 – 80 Vestas 2 MW – 2002

Followed conversion of 2 A2SEA crane vessels.
Made marine operation methods for A2SEA crane vessels.
Developed method statements and risk assessments for turbine installation.
Client representative on crane vessels during turbine installation.

Customer: Vestas UK